For the latest in our Meet the Members series, Li Tian, Managing Director of Liri Tents, takes us behind the scenes of the 140th Canton Fair.

Between phases, his team had just 48 hours to dismantle around 20,000 m² of temporary structures and install another 20,000 m². Li explains how they pulled it off, what a 40-metre clear span makes possible and why it pays to bring structural engineers in early.

What are Liri Tents’ roots, and where do you fit into the company’s story?

Liri was the first company in China to manufacture aluminium clear-span tents. Our founder, Mr Liang, is a structural engineer, and that engineering foundation is still central to how we approach technical design. I’m the second person to lead the business.

Liri has worked on the Canton Fair since 2001. How has the brief changed, and what made the 140th edition different?

In the early days, we supplied a few thousand square metres of tents for outdoor exhibition halls, security checkpoints, vehicle parking and other support facilities. As the fair grew and moved to the Pazhou Complex, its exhibition area eventually reached 500,000 m².

Our role grew with it. We now deliver more than 70,000 m² of temporary space per session and roughly 300,000 m² of outdoor exhibition tents over the course of a year. The 140th edition was the largest to date and saw the fair adopt our new Thermo Cube tent system with horizontal glass walls, alongside several new designs.

What was the biggest challenge in delivering 70,000 m² of temporary exhibition space?

Coordinating the work on site while managing the weather. Heavy rain and gusty winds can arrive suddenly, and erecting aluminium frames is especially sensitive to those conditions. We built contingency time into the schedule.

The turnaround between phases was another challenge. Each of the three phases has a different group of exhibitors, so the location and layout of the halls change. Between phases, we had just 48 hours to dismantle around 20,000 m² of structures and install another 20,000 m².

What did the 40-metre clear spans and eight-metre eaves make possible?

A 40-metre clear span gives exhibitors uninterrupted floor space. They can bring in large machinery, build full-width island stands and create open demonstration or networking areas. That’s particularly valuable for industrial exhibitors.

The eight-metre eaves give organisers room for lighting rigs, overhead signage and mezzanine meeting areas. Using the same Cube design across the site gives the halls a consistent look, while the glass walls bring in natural light.

Is there a moment from the build that stands out?

Watching the halls take shape one after another. We went from scorching midday sun to sudden wind and heavy rain, and the installation team still delivered on schedule. Seeing how well they worked together through those changes is what stays with me.

What should organisers decide early when planning a large temporary exhibition space?

Agree the structural specifications and load requirements before finalising stand layouts and visitor routes. Bringing structural engineers in early can save costly rework and help keep the project on schedule.

Where do you see the biggest opportunities for temporary structures over the next few years?

The Middle East is one of the biggest opportunities I see. I hope the current conflicts come to an end soon so the market can return to normal. The US is also a very active market, supported by a strong economy.